Glenfield to Leppington Rail Link

 


 

 

Metro Resources Group was engaged for the construction and delivery of 680 OHW structures foundations.


Continuous consultation and programming meetings were integral parts of the planning process to ensure planned target dates were achieved with maximum quality and minimum disruption with other work groups.


In addition, Metro Resources Group teams were required to assist in the delivery and completion of CSR, local route, signal base installation, mandrelling / proofing of all cable routes.

 

 

 

   

Principle Contractors:

John Holland Civil

Estimated Project Value:

AU $2.5mil

Project Location:

Glenfield to Leppington (SWLR)

Approx. Duration:

16 Months

 

 

Footings

 


 

Signle Base


Combined Service Routes